WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5186

Discipline/Origin

Drilling
Own Experience

Well

Carmen
35/10-10S

Date created

2023/05/20
931 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Yantai


What happened in Reservoir section:
Drilled 8 1/2″ section with 5 7/8″ DP with 1400-1500 lpm and low ROP, saw ECD up to 18 points.
MW was 1.72 and ECD measured to 1.88 sg.

What Was Planned

Use 5 7/8″ DP for the whole section drilling 8 1/2″ hole.
Simulations drilling 8 1/2″ using 5 7/8″ DP with 1.85 sg with 1500 lpm flow rate and ROP of 20 m/hr gives ECD of 10 points to 1.948 sg.

What Was Learned

Higher than simulated/expected ECD observed that may cause fractures. Loss/gain situation for the deepend section in 8 1/2″ section (4050-4089 m MD).

What Actions Are Required

Use of tapered DP string, using 5 7/8″ and 5″ will decrease ECD with some points. Has to be simulated to see difference. But just some few points decrease might have a big difference, may for example never experience loss/gain situations.

Additional Documentation


DDR-Carmen-Day-48.pdf